Tech Way

Opportunity

Status

Estimated Start:

Total Annual Savings

Project Cost:

Project Payback:  

Description

Capital Upgrade - High Efficiency Boiler Replacement

Not Started

FY 2025

$4,200

$60,500

14.6

Replace boiler with high efficiency condensing boiler. Reprogram bypass valve to open only when needed for minimum flow control.

Recommendation: 

See above Description.